PROJECTS |
|
|
| APO CEMENT REPAIR OF FLENDER GEARS |
Client |
: |
APO CEMENT |
| Project Location |
: |
Naga, Cebu City |
| Execution Period |
: |
February – June 1999 |
| Cargo Nature |
: |
Flender Gear |
| No. of Heavylifts |
: |
4 Units Flender Gear |
| Scope of Works |
: |
Jacking of Flender Gears from the foundation and skidding out of the plant, lifting using a mobile crane for loading unto the trailer going to repair shop, and delivery back to the power plant including unloading and skidding back inside the power plant. |
| Remarks |
|
|
| Same procedure was repeated four (4) times. |
| |
|
|
|
|
|